Specifies the quantity of machines or personnel that can perform their expected functions simultaneously. This is only defined for the machine center level and reduces the production lead times of the order.

The program automatically fills in this field when you enter the number of a machine or work center on the line, but you can change it.

Example:

If processing normally requires a period of four hours, the processing time will be reduced significantly by using two machines.

Tip

See Also