Contains the value that will be used for the calculation of capacity.
If the capacity is calculated in units, the formula is Quantity = Output Quantity + Scrap Quantity.
If the capacity is calculated in time, the formula is Quantity = (Setup Time +) Run Time.
The setup time is only included if you have checkmarked the Cost Incl. Setup field in the manufacturing setup.