Open the Machine Center Load/Bar window.

Shows a list of the machine centers, which according to the actual planning are overloaded. The efficiency or overloading is shown by efficiency bars.

Options

Starting Date: Enter the starting date for the evaluation.

No. of Periods: Enter the number of time intervals the evaluation is to be created for.

Period Length: Enter the length of the time interval, for example 1W = one week.

Load bigger than (pct.): Here you can enter a filter to print only work centers whose loads exceed this percentage, for example, if you want to print all work centers with a load of over 95% in order to troubleshoot a particular problem.

Tip