Open the Resource Allocated per Job window.

You use the Resource Allocated per Job matrix to view and change the amounts of measuring units for resources allocated to the various jobs in different time periods.

You can select a time interval in the View by field.

After you fill in the fields and set filters in the Resource Allocated per Job window, click Show Matrix to view the matrix.

The lines are divided into two parts. The left side contains the jobs, with a line for each job, and the right side shows the amounts of measuring units per selected time period.

Tip

See Also